Waste project 2024 Archives - Award Winning Civil Engineering Company /category/case-studies/waste-project-2024/ Providing a sustainable future Wed, 04 Sep 2024 15:34:20 +0000 en-GB hourly 1 https://wordpress.org/?v=6.9.4 FCC Framework /fcc-framework/ Wed, 04 Sep 2024 14:57:24 +0000 /?p=9959 Running for four years to 2021, Jones Bros successfully undertook £43m of work for the waste management company, delivered in-house by one of the largest plant fleets in the UK. Works included: Operating 10-15 projects, [read more]

For further info on this, please click here FCC Framework.

]]>
Running for four years to 2021, Jones Bros successfully undertook £43m of work for the waste management company, delivered in-house by one of the largest plant fleets in the UK.

Works included:

  • Operating 10-15 projects, which ran simultaneously
  • In excess of 1.5million m2 capping
  • More than 40 landfill cell voids delivered
  • Being reactive to unscheduled project activity

For further info on this, please click here FCC Framework.

]]>
Erin Landfill Site /erin-landfill-site/ Wed, 04 Sep 2024 14:56:28 +0000 /?p=9961 Activity at the landfill site in Markham Vale, Chesterfield, was split into three areas: Leachate reception area Permanent capping Cell 4a, 4b, and asbestos cell extension. Works included: Constructing a fully contained concrete leachate reception [read more]

For further info on this, please click here Erin Landfill Site.

]]>
Activity at the landfill site in Markham Vale, Chesterfield, was split into three areas:

  • Leachate reception area
  • Permanent capping
  • Cell 4a, 4b, and asbestos cell extension.

Works included:

  • Constructing a fully contained concrete leachate reception area, including a completely automated leachate extraction system
  • Permanent capping activity that featured 21,000m2 of fully welded LLDPE and protector geotextiles and two layers of restoration soils
  • Removing 108,000m3 of soil
  • Installation of a ground water extraction system with 700m fully welded HDPE pipework into chamber and pumping system
  • Installation of 35,000m3 of engineered barrier and 35,000m2 of fully welded HDPE and protector geotextile
  • Installation of full leachate extraction system featuring bespoke chambers with 800m of HDPE pipework and filter geotextile
  • Installation of internal haul road and turnaround pad
  • Geophysical detection on all cells

For further info on this, please click here Erin Landfill Site.

]]>
High Heavens Waste Transfer Station /high-heavens-waste-transfer-station-nr-high-wycombe-bucks/ Tue, 22 Nov 2016 16:32:11 +0000 /?p=3601 Construction of waste recycling facility and hard standing area on a former landfill site. The site’s original ground make-up comprised of approx 5m of household waste, covered with a thin layer of capping. Works involved: [read more]

For further info on this, please click here High Heavens Waste Transfer Station.

]]>
Construction of waste recycling facility and hard standing area on a former landfill site. The site’s original ground make-up comprised of approx 5m of household waste, covered with a thin layer of capping.

Works involved:

  • Groundworks – 105 pre-cast driven piles installed up to depth of 12m, R.C. pile caps  c/w holding down bolts, constructed on the piles in preparation for the steel frame building
  • Ground bearing slab – (50m x 40m) – 200mm thick with 2 layers of A393 mesh and C60 concrete – a dry shake mix finish was applied for an abrasion resistance finish.
  • Construction of 11m high cladded steel framed building (50m x 40m) with seven 6m high roller shutter doors
  • Construction of 2500m2 of external hard standing – 200mm thick PAV2 concrete slab with single layer of A252 steel mesh
  • Drainage – 550L/m of 300mm twin wall underground drainage laid for the surface water to     then flow through a 14000 litre interceptor and into an attenuation lagoon. From here the water runs through a penstock valve and hydro brake, finally into a soakaway. A rainwater harvesting tank was installed to recycle rainwater from the WTS roof
  • Reinforced concrete push walls – 110L/m, 350mm thick, cast in-situ, 4.0m high
  • Office and welfare facilities (80m2) – constructed and installed
  • Retaining wall – 50L/m, 400mm thick cast in-situ 1-4m high retaining wall, adjacent to existing access road
  • Weighbridges – installation of 2 pit weighbridges 

     

For further info on this, please click here High Heavens Waste Transfer Station.

]]>
Wrexham MBT facility /mbt-facility-phase-2-wrexham-recycling-park/ Tue, 22 Nov 2016 14:18:53 +0000 /?p=3565 Construction of building to house mechanical biological treatment (MBT) plant at Wrexham Recycling Park. The plant extracts recyclable material from domestic refuse and transforms the residue into fuel for multifuel power generation facilities. The works [read more]

For further info on this, please click here Wrexham MBT facility.

]]>
Construction of building to house mechanical biological treatment (MBT) plant at Wrexham Recycling Park. The plant extracts recyclable material from domestic refuse and transforms the residue into fuel for multifuel power generation facilities.

The works consisted of:

  • Brown field site – full remediation works undertaken, including removal of asbestos, prior to commencement of civils works.
  • Construction of steel framed building 140m x 67m to house the machinery – 7000m3 of structural concrete placed.
  • Construction of 5 concrete drying tunnels (8m x 5.5m x 32m long)
  • Stats diversion
  • Drainage 940m (MDPE/twinwall) 620m foul drainage – incorporating process drainage.
  • Value engineering within the design from Stats diversions to contaminated waste dealt with on site.

For further info on this, please click here Wrexham MBT facility.

]]>